|

|
Aim
The aim of our QS Department is to work
closely with the Contractor's QS, monitoring all the financial aspects
of the contract, which will lead to: -
| a. |
A
scaffold package price that is closer to the end result. |
| b. |
A
closer and understanding relationship between contractor
and scaffold contractor.
|
| c. |
Tighter
control by site management of variations carried out.
|
| d. |
More
awareness by trade contractors that they will be liable
for scaffold carried out on their behalf - scaffold request
system.
|
| e. |
Early
warning of sub-contractor liabilities.
|
| f. |
A
satisfactory final account to all parties. |
With use of e-mail, we can
send all valuations and breakdown to sites in their formulated context
to enable further sorting and analysis for valuations, contra charges
and financial monitoring.
TOP
Our Valuation
Procedures
The valuation of the contract works
could be carried out in a similar way to that which preliminary
items are claimed from the PQS. i.e. an expenditure schedule of
the works related to the contract programme. Major changes to work
are carried out on an add and omit basis. We do prefer to agree
this with the Contractor's QS on exactly the same basis prior to
agreement with the PQS. There will be no conflict on payment and
liabilities will be known in advance.
Valuation
of variations is always a major bone of contention. Does the work
relate back to the original estimate, should it be valued at a schedule
of rates or should it be carried out on a Daywork basis? We know
what return we require on a man carrying out variations to include
all labour erecting, adapting, dismantling, transport, consumables
and hire of scaffold materials. As long as the rate per man is realistic,
all variations could be based on the time taken only. This would
be easier to monitor by your Manager than trying to remember a measurement
of scaffold and the erect date, as well as the dismantle date. Offsetting
contra charges against the various trades would be just the same,
in that they can be valued in accordance with responsibilities noted
on site instructions and scaffold request forms.
TOP
How
our account is laid out: -
| a.
|
Measured
works (original quotation). |
| b.
|
Breakdowns
of measured works claimed on a progressive basis e.g. 1000m
claimed to date out of a total of 2000m. |
| c. |
Priced
variations. |
| d. |
Guardrail
schedule. |
| e. |
Daily
variations account arising on instruction for immediate
action and related to a schedule of rates. |
| f. |
Grand
summary of all of the above. |
| g. |
Final account projection. This has
the facility for the contractor to predict final dismantling
dates to project hire and variations forward. |
TOP
Measured
works are presented showing the following information: -
| a. |
The
quotation and item number.
|
| b. |
Heading/description
of the scaffold.
|
| c. |
Value
of the item and the hire period quoted.
|
| d. |
The
split, generally 2/3 erection and 1/3 dismantle. Adaptions
are generally shown separately.
|
| e. |
Date
erected and dismantled.
|
| f. |
The
amount claimed on the current valuation.
|
| g. |
The
further hire commencement date and any further hire if applicable.
|
| h. |
On hire dates begin with the signature
on a handover certificate. We would suggest that a dismantle
instruction be issued by you at the appropriate time. This
would end all arguments and disputes as to when the scaffold
came down. It would also focus the mind if the instruction
was issued, but not quite ready, as to who is responsible
and therefore who should be charged. |
TOP
Daily Variations/Instructions:-
| a. |
The
Contractor should specify one member of the management team
to look after the scaffolding package on site. If more personnel
are involved, this can lead to confliction and duplication
of scaffolding in areas e.g. scaffolds being dismantled earlier
than necessary and then being re-erected. |
| b. |
The trade contractors
should issue a Scaffold Request Form to the Main Contractor's
scaffold coordinator to instruct daily variations. These should
state whether they are to be paid for by Trade contactor,
Main Contractor or trade to be contra-charged. This information
can then be passed onto the Surveyor. |
| c. |
The instruction
needs to clearly identify the work that is to be carried out;
who the work was for e.g. trade or company and the reason
the work was carried out. If all this information is on the
instruction, the variation account can be detailed accordingly.
|
| d. |
Each
variation is attributed either to a sub-contractor, an Architects
Instruction, the Main Contractor or to site safety. |
| e. |
When the item of scaffold
is finished with, it is dismantled and recorded on our daily
work sheets. We re-iterate that at this point a scaffold dismantle
request or instruction should be issued with the date clearly
stated. |
| f. |
Once the variation has been established,
it is charged in the scaffold account using one of the methods
described in item 12. The item is then priced using the schedule
of rates with the information listed under the following headings:
- |
i.
Location gridline and floor level.
ii.
Description of the scaffold e.g. independent, tower, etc.
iii.
Reason/trade e.g. for bricklayer.
iv.
Site instruction and work sheet numbers.
v.
Dimensions.
vi.
Dates erected and dismantled.
vii.
Quantities and rates.
viii.
Split for labour and materials totals.
TOP
Additional
information – Sorting/Final Account:-
| a. |
The daily variation account
will be able to be coded for each trade. This will enable
data sorting throughout the contract to establish the liability
for scaffold against each trade. |
| b. |
Final account projection – each monthly
valuation can be sent including a projected final account,
which compares against the works to date. This is shown under
the following headings:- |
i.
Quoted value.
ii.
Anglewest claimed to date.
iii.
Further hire to date.
iv.
Final account (sum of 1 & 3).
v.
Daily variations and guardrails are shown as to date figures
or projected forward each month, based on the current amount
claimed.
vi.
Summary comparing actual to date against projected.
TOP |